HSS.2A INSPECTION ZONE CONFIGURATION

HSS.2A INSPECTION ZONE CONFIGURATION

The inspection zone is the area a person walks through during screening. The HSS system collects data from the moment a person enters the zone until they exit. Once a person leaves the zone, the inspection is considered complete.

To improve efficiency, it’s recommended to guide people through the zone using barriers, tape, or other flow control methods.


Warning
The placement of flow barriers must be approved by APSTEC technical support before use.

HSS inspection zone layout


    • Related Articles

    • HSR.4B INSPECTION ZONE AND CONFIGURATIONS

      The inspection zone is the area where a person must walk straight through the HSR system. The system starts scanning when the person enters and finishes when they leave the zone. There are two setup options depending on how people move: 1. ...
    • HSS.2A DIMENSIONS

      External dimensions - 2245 mm х 1341 mm х 580 mm Required minimal space for HSS installation - 1.8 m x 1.5 m Passage width - 1.2 m The Inspection zone of HSS system
    • HSS.2A OPERATING

      Preparing for Operation: Inspect the HSS pillars – check for any visible mechanical damage. Make sure the built-in camera lenses are not damaged or obstructed. Check the inspection zone – there should be no objects or people inside. Start up the ...
    • HSS.2A USAGE RECOMMENDATIONS

      First Year of Operation After the first year, a qualified engineer should perform a full system inspection: Check all key components, including electronic and mechanical parts Inspect electrical connections for oxidation, looseness, or wear Test ...
    • HSS.2A OPERATION CONDITIONS

      PARAMETER VALUE Recommended temperature range +3°C to +40°С Maximum temperature range -10°C to +55°С Humidity 5% to 90%, non-condensing Atmospheric pressure 630mmHg to 800mmHg Notes: The HSS system can handle high temperatures for short periods. ...